Plots 3,4,5,6 Timber Frames Nearly Finnished.
This week starts with a well needed couple of days to clear the site, skips are coming and going and the site is starting to look organised ready for the next phase. Last week was very busy with sometimes as
Timber Frames Going Up
Monday the 17th saw the arrival of the timber frames along with a team of expert installation guys supplied by TTFC. Once the crane was positioned the guys started erecting the houses working very quickly to roof height. By the
White Mill Ground Work 15/11/2014
Ground work nearly complete with scaffolding going up in preparation for the timber frames. You can see the great views over the valley and park land. This is the view they will have looking out the back. Aerial Photography courtesy of